Interpretation Response #PI-96-001 ([Michigan Public Service Commission] [Kris Brock])
Below is the interpretation response detail and a list of regulations sections applicable to this response.
Interpretation Response Details
Response Publish Date:
Company Name: Michigan Public Service Commission
Individual Name: Kris Brock
Location State: MI Country: US
View the Interpretation Document
Response text:
Mr. Kris Brock
Gas Safety Program
Michigan Public Service Commission
6545 Mercantile Way
Lansing, Michigan 48909-7721
Dear Mr. Brock:
This is in response to your September 27, 1995, letter granting a waiver to Consumers Power Company from Rule 321(1) of the Michigan Gas Safety Code to permit the aboveground installation of a 4-inch plastic gas main in a 6-inch steel casing pipe across a bridge in the City of Warren, Macomb County. Rule 321(1) contains the same requirement as 49 CFR 192.321(a) which is that plastic pipe must be installed below ground level. Although our response is beyond the 60 days from written notification as prescribed in 49 U.S.C. 60118(d), we believe that a response should be provided.
We have reviewed the July 19, 1995, waiver application from Consumers Power Company and the Commission's September 21, 1995, order waiving compliance with Rule 321(1). Based on the facts in these two documents, we see no reason to object to the Commission's decision to grant the waiver.
Sincerely,
Richard B. Felder
Associate Administrator for
Pipeline Safety
Regulation Sections
Section | Subject |
---|---|
192.321 | Installation of plastic pipe |