Interpretation Response #PI-82-010 ([Williams Pipe Line Company] [R. G. Keearns])
Below is the interpretation response detail and a list of regulations sections applicable to this response.
Interpretation Response Details
Response Publish Date:
Company Name: Williams Pipe Line Company
Individual Name: R. G. Keearns
Location State: OK Country: US
View the Interpretation Document
Response text:
Mr. R. G. Keearns
Manager of Environmental Affairs
and Pipeline Safety
Williams Pipe Line Company
P.O. Box 3448 Tulsa, OK 74101
Dear Mr. Keearns:
This is in response to your letter dated December 2, 1981, concerning the application of §195.304(b) to two factual situations.
The enclosed pipeline safety regulatory interpretation explains §195.304(b) and gives its application to the two factual situations presented in your letter.
We hope this meets your needs.
Sincerely,
/signed
Melvin A Judah
Acting Associate Director
for Pipeline Safety Regulation
Materials Transportation Bureau
Enclosure
DEPARTMENT OF TRANSPORTATION
RESEARCH AND SPECIAL PROGRAMS ADMINISTRATION
MATERIALS TRANSPORTATION BUREAU
PIPELINE SAFETY REGULATORY INTERPRETATION
Note: A pipeline safety regulatory interpretation applies a particular rule to a particular set of facts and circumstances, and, as such, may be relied upon only by those persons to whom the interpretation is specifically addressed.
SECTION: 195.304(b)
SUBJECT: Testing Components
FACTS: The following facts are given in a letter dated December 2, 1981, from R. G. Keearns, Williams Pipe Line Company, to the Office of Pipeline Safety Regulation
Case I
An existing pipeline was cut to install a new pump. A new check valve was installed in the existing line together with new suction and discharge piping, tees, ells, valves, and interconnected pump. The pipe was pretested. The pump was tested by the manufacturer at the factory. All other items were manufactured to the same standard as a tested prototype. The tie-in welds were radiographed.
Question: Does this pump station installation qualify as the "only item being . . . added" under §195.304(b) and, therefore, excepted from the hydrostatic test requirement of §195.302(a)?
Case II
In a header, four flanged end valves were replaced with identical new valves which were manufactured to the same standard as a tested prototype. Because only valves were replaced, do they qualify as the "only item being replaced" under §195.304(b) and are, therefore, excepted from the test requirement of §195.302(a)?
Interpretation: Section 195.304(b) was adopted on November 2, 1970, as Amendment 195-2, Docket No. HM-6. The preamble to that amendment makes clear that §195.304(b) applies only to single item replacements or additions. In Case I, more than a single item has been added, and in Case II more than a single item has been replaced. Therefore, in both cases, §195.304(b) does not apply and hydrostatic testing is required under §195.302(a).
Melvin A. Judah
Acting Associate Director
for Pipeline Safety Regulation
Materials Transportation Bureau
Regulation Sections
Section | Subject |
---|---|
195.304 | Test pressure |