Interpretation Response #PI-79-023 ([NIBCO Inc.] [Don Wagoner])
Below is the interpretation response detail and a list of regulations sections applicable to this response.
Interpretation Response Details
Response Publish Date:
Company Name: NIBCO Inc.
Individual Name: Don Wagoner
Location State: IN Country: US
View the Interpretation Document
Response text:
Mr. Don Wagoner
Product Manager - Convoluted Flange
NIBCO Inc.
P. O. Box 1167
Elkhart, IN 46515
Dear Mr. Wagoner:
Thank you for your letter of May 31, 1979, and the results of the tests and stress analysis concerning the use of convoluted flanges for pipeline application.
Our letter of September 21, 1977, to Mr. Gunter Schlicht, Pipetech, Inc., (copy of which you enclosed) outlined what action we considered necessary to determine that the convoluted flange would: (1) provide an equivalent level of safety to that provided by flanges which meet the minimum requirements of the referenced specifications cited in Section 192.147 of Part 192, Code of Federal Regulations, and (2) be suitable for the service in which it is to be used under Section 195.126 of Part 195, Code of Federal Regulations, namely to develop a detailed design and stress analysis supported by a proof test under the provisions of UG-101 of the ASME Boiler and Pressure Vessel Code. You must assure yourself that the analysis and proof testing undertaken on your behalf support these conclusions before the convoluted flange can be used on pipelines subject to Parts 192 or 195.
We can neither endorse nor reject the convoluted flange as we do not approve proprietary products for use in pipelines.
Sincerely,
/signed/
Cesar DeLeon
Associate Director for
Pipeline Safety Regulation
Materials Transportation Bureau
Regulation Sections
Section | Subject |
---|---|
192.147 | Flanges and flange accessories |