Interpretation Response #PI-93-025
Below is the interpretation response detail and a list of regulations sections applicable to this response.
Interpretation Response Details
May 26, 1993
Mr. Marti Marek
Manager, Compliance and Operations Audit Staff
Southwest Gas Corporation
P.O. Box 98510
5241 Spring Mountain Road
Las Vegas, NV 89193-8510
Dear Marti Marek:
I am sorry to have taken so long to respond to your letter of November 23, 1992. You asked whether meter turn-on operations must be included within an operation and maintenance plan under 49 CFR 192.605.
We received a letter on this subject from Dan Weaklend of the Arizona Corporation Commission (enclosed). We are of the same opinion as Mr. Weaklend that the plan must cover turn-on operations. However, it is §192.605(a), not §192.605(b), that requires inclusion of the operations within the plan.
Sincerely,
Cesar De Leon
Director, Regulatory Programs
Office of Pipeline Safety
Enclosure
Regulation Sections
Section | Subject |
---|---|
§ 192.605 | Procedural manual for operations, maintenance, and emergencies |