Interpretation Response #PI-74-004 ([Dallas Engineering, Inc.] [Dois D. Dallas])
Below is the interpretation response detail and a list of regulations sections applicable to this response.
Interpretation Response Details
Response Publish Date:
Company Name: Dallas Engineering, Inc.
Individual Name: Dois D. Dallas
Location State: ND Country: US
View the Interpretation Document
Response text:
January 24, 1974
Mr. Dois D. Dallas
Petroleum Engineer
Dallas Engineering, Inc.
P.O. Box 594
Tioga, ND 58852
Dear Mr. Dallas:
In your letter of January 17, 1974, you ask what protection should be provided for insulated 3/4-inch metallic riser pipes. Risers are to be coated and cathodically protected as required by Section 192.455. The level of protection must meet one or more of the criteria contained in Section 192.463. The frequency for monitoring service risers is covered by Section 192.465.
We trust this answers your question. If you desire any further information, please advise.
Sincerely,
'signed'
Joseph C. Caldwell
Director
Office of Pipeline Safety