Interpretation Response #PI-75-0116
Below is the interpretation response detail and a list of regulations sections applicable to this response.
Interpretation Response Details
Response Publish Date:
Company Name:
Individual Name:
Location State: OK Country: US
View the Interpretation Document
Response text:
December 2, 1975
Mr. J.L. Williams
Williams Brothers Engineering Company
6600 South Yale Avenue
Tulsa, OK 74136
Dear Mr. Williams:
This is with regard to the telephonic conversation between you and Mr. George L. Mocharko of this Office concerning installing gas pipelines uncased under a hard surface road.
Your interpretation of 49 CPR §192.103, §192.105, and §192.111(b)(2) is correct per your letter and attachments dated August 4, 1975.
We trust this adequately responds to your inquiry.
Sincerely,
SIGNED
Cesar DeLeon Acting Director Office of Pipeline Safety Operations