January 4, 1971
Mr. James B. Williams
Utilities Engineer
Alabama Public Service Commission
P.O. Box 881
Montgomery, Alabama 36102
Dear Mr. Williams:
This is in reply to your letter of December 22, 1970, concerning 49 CFR, Section 192.625,
odorization of gas.
If the line involved is operated at 20% or more of SMYS, under 49 CFR, Section 192.625 as
amended, there is requirement for odorization. If it is operated at less than 20% SMYS you may
initiate a waiver proceeding under Section 3(e) of the Natural Gas Pipeline Safety Act.
Thank you for your interest in pipeline safety.
Sincerely,
/signed/
Joseph C. Caldwell
Director, Acting
Office of Pipeline Safety
Regulation Sections
Section | Subject |
---|---|
192.625 | Odorization of gas |