ExxonMobil - 3-29-13 Arkansas Pipeline Failure
PHMSA issued a Corrective Action Order to ExxonMobil Pipeline Company as a result of the operator's March 29, 2013 failure in Mayflower, Arkansas. The order prevents ExxonMobil from restarting operations on the failed segment until the agency is satisfied with repairs and is confident that all immediate safety concerns have been addressed.
Inspection Reports
- Mobil 1994 Joint Team Inspection Report
- Mobil 1997 Inspection Report
- Mobil 1999 Inspection Report
- Mobil 2001 Inspection Report
- Mobil 2003 Inspection Report
- IU3944 Standard Inspection Report - 2001 to 2002
- 11912 Standard Inspection Report - 2003
- IU3944 Standard Inspection Report - 2004
- IU3944 Standard Inspection Report - Nov 2007
- 2010 Pegasus Closed Inspection-Final Order
- 2010 Pegasus Closed Inspection-NOPV
- 2010 Pegasus Closed Inspection-Violation Report
- 220025006 Violation Report
- 220025006_final order_09052002
- 220025006 Notice Letter 02122002
- Mobil 1995 Accident Report Hazardous Liquid Pipeline
NRC Reports
Pegasus - Mayflower Spill Corrective Action Order
Miscellaneous Documentation
- Mobil Pipe Line Co - Hazardous Liquid Accident - Original - 20130151 - 17953
- Wabasca Crude Oil ExxonMobil MSDS
- April Correspondence - EM and PHMSA
- Excavation and Removal Plan